To provide a frame body that can make connection time of the prefabricated frame body and piles extremely short and obtain a connection structure of high strength while allowing construction errors of the piles, and to provide the connection structure of the frame body and piles.
The frame body 1 is fabricated in a factory by mounting beam members 4, 4 to side faces of shield pipes 2 formed of steel pipes or the like, and installing column members 3 inserted from one-side openings of the shield pipes 2. Pile head reinforcements 51, 51 of the pile 5 constructed in the ground are stored in the shield pipes 2, 2 through the other-side openings of the shield pipes 2, and a filler 6 is filled in the shield pipes 2 and hardened to integrate the pipes 5, 5 and the frame body 1, thus forming the connection structure.
JP2000257006A | 2000-09-19 | |||
JPH0726568A | 1995-01-27 |
Sekiya Mitsuo
Yasushi Hayakawa
Ishikawa Takiharu