To provide a pit reinforcement assembly method capable of reducing a period and a cost for assembling pit reinforcements and assuring an assembly accuracy.
This pit reinforcement assembly method comprises the steps of forming a scaffold 12 for reinforcement assembly in an excavated pit 10, temporarily and annularly assembling hoop reinforcements 20 for multiple stages by using an assembly device 18 on a ground 16 around the pit 10, carrying the temporarily assembled multiple stages of hoop reinforcements 20, in order, into the pit 10 and connecting the multiple stages of hoop reinforcements 20 to the inside of the pit 10 by using the scaffold 12, inserting the main reinforcements 56a and 56b into the pit 10 and connecting the main reinforcements 56a and 56b to the hoop reinforcements 20 by using the scaffold 12, and dismantling and carrying out the scaffold 12.