The present invention relates to a method and system for analyzing and optimizing a key path in a debugging stage of a nuclear power unit. The method comprises the following steps: determining key nodes of the key path in the debugging stage of the nuclear power unit; performing key path analysis according to the key nodes to obtain a key path analysis result; and performing key path optimization according to the key path analysis result to obtain an optimized key path. According to the present invention, the key nodes of the key path in the debugging stage of the nuclear power unit are analyzed and determined, and the key path is accurately recognized, optimized and adjusted, such that an optimal key path can be obtained without using an early-stage unit as a reference, thereby ensuring ordered operation of a project.

Inventors:
HU JIANHUA (CN)
GUO DONGHUI (CN)
WANG ZHIMING (CN)
WANG HONGLIN (CN)
LU JUNYU (CN)
ZHOU YUJIA (CN)
GAO YUAN (CN)
CHEN SHIJI (CN)
TIAN LICHUANG (CN)
Application Number:
PCT/CN2023/100269
Publication Date:
April 25, 2024
Filing Date:
June 14, 2023
Export Citation:
Click for automatic bibliography generation   Help
Assignee:
CHINA NUCLEAR POWER ENG CO LTD (CN)
CHINA GENERAL NUCLEAR POWER (CN)
CGN POWER CO LTD (CN)
International Classes:
G06Q10/04
Foreign References:
CN115640892A2023-01-24
CN113190895A2021-07-30
CN113408856A2021-09-17
JPH05250350A1993-09-28
KR20200076554A2020-06-29
Other References:
纪涛 (JI, TAO): "基于约束理论及关键链法的核电站设备调试项目管理研究 (Non-official translation: Research on Nuclear Power Plant Equipment Commissioning Project Management Based on Constraint Theory and Critical Chain Method)", 万方平台 (NON-OFFICIAL TRANSLATION: WANGFANG PLATFORM), 18 September 2014 (2014-09-18)
CHEN, HAO: "Analysis of Key Points for Progress Optimization in the Preparation Stage of Joint Commissioning of Nuclear Power Units", SCIENCE AND TECHNOLOGY & INNOVATION, CN, no. 16, 1 January 2019 (2019-01-01), CN , pages 121 - 122, XP093162936, ISSN: 2095-6835, DOI: 10.15913/j.cnki.kjycx.2019.16.052