Abstract:
A method for wireline intervention in an subsea well from a floating vessel(4) comprises: a) arranging a tubular tool riser(1) in a substantially horizontal position at a deck(4A) of the vessel(4); b) connecting a wireline assembly(7A) to a wireline(7) that is connected to a winch(7B)at the deck (4A); c) inserting the wireline assembly(7A) into the tool riser (1) such that the wireline (7) passes along a riser sheave(8) connected to a first end(1A) of the tool riser(1); d) connecting the first end(1A) of the tool riser(1) to a crane hook(2) that lifts the tool riser(1)in an upright position above a guide sleeve(5)that is connected to a side wall(4B) of the vessel(4) adjacent to the deck(4A); f) inducing the crane to lower the tool riser (1) through the guide sleeve(5) such that the second end(1B) of the tool riser(1) is located subsea and the first end(1A) of the tool riser(1) and the riser sheave(8) are located above the deck(4A); and g) inducing a crane heave compensation mechanism to control the motion of the tool riser(1) and riser sheave(8) relative to the seafloor while unreeling the wireline(7) from the winch(7B) such that the wireline assembly(7A) is lowered from the tool riser(1) through the water 11 into an subsea well.

Inventors:
MORRIS COLIN (US)
BUCHAN MARTIN (AU)
LARIMORE DAVID RUSS (US)
BOECHAT DOS SANTOS GLORIA NIVEA (BR)
CERVO GUSTAVO (BR)
DAVIS SCOTT WINFIELD (US)
GORDON SCOTT ALISTAIR (US)
KLEIN MARK JAMES (BR)
PAQUETTE MARC GERARD (US)
Application Number:
PCT/US2012/070672
Publication Date:
July 04, 2013
Filing Date:
December 19, 2012
Export Citation:
Click for automatic bibliography generation   Help
Assignee:
SHELL OIL CO (US)
SHELL INT RESEARCH (NL)
International Classes:
E21B19/09; B66D1/50; E21B19/02; E21B19/15; E21B47/01
Foreign References:
EP1070828A22001-01-24
US2809436A1957-10-15
GB2292760A1996-03-06
US3650323A1972-03-21
US6216789B12001-04-17
Attorney, Agent or Firm:
CARRUTH, James D. (One Shell PlazaP.O. Box 246, Houston TX, US)
Download PDF:
Claims:
C L A I M S

1. A method for wireline intervention in an subsea well from a floating vessel, the

method comprising:

a) arranging a tubular tool riser in a substantially horizontal position at a deck of the vessel;

b) connecting a wireline assembly to a wireline that is connected to a winch arranged at the deck;

c) inserting the wireline assembly and pass the wireline through a first end of the tool riser into said riser such that the wireline passes along a riser sheave connected to the first end of the tool riser;

d) connecting the first end of the tool riser to a crane that lifts the tool riser in a substantially vertical position above the deck, whilst unreeling the wireline from the winch such that the wireline assembly remains located within the tool riser;

e) inducing the crane to move a second end of the tool riser above a guide sleeve which is connected to a side wall of the vessel adjacent to the deck;

f) inducing the crane to lower the tool riser through the guide sleeve such that the second end of the tool riser is located subsea and the first end of the tool riser and the riser sheave are located above the deck; and

g) inducing a crane heave compensation mechanism to control the motion of the tool riser and riser sheave relative to the seafloor while unreeling the wireline from the winch such that the wireline assembly is lowered from the tool riser through the water into the well.

2. The method of claim 1, wherein the first end of the tool riser is connected by a

hoisting cable to a hook which is connected to a fall line of the crane.

3. The method of claim 2, wherein the hook is connected to a single fall line of the crane and the crane heave compensation mechanism is configured to maintain the hook substantially stationary relative to the seafloor, thereby providing heave compensation to the wireline assembly.

4. The method of claim 2, wherein wireline passes through a deck sheave which is

connected to the deck adjacent to the sleeve and the hook is connected to a hoisting sheave which is connected by a double fall crane line to the crane and the heave compensation mechanism is configured to substantially halve reduce heave motion of the hook relative to heave motion of the vessel and inducing the deck sheave and riser sheave to provide heave compensation to the wireline assembly.

5. The method of any one of claims 1-4, wherein the wireline assembly is inserted into an subsea oil and/or gas production well to monitor the condition of downhole well equipment and of the oil and/or gas containing formation surrounding the well and/or to monitor, manage and/or optimize downhole fluid flow through the formation and the well and/or to alter the state of the well and/or well geometry during, or at the end of its productive life.

6. The method of claim 5, wherein the wireline assembly is first lowered into the well and subsequently pulled up through the well at a predetermined speed by winching up the wireline while activating monitoring equipment in the wireline assembly.

7. A system for wireline intervention into an subsea well from a floating vessel, the

system comprising:

a) a floating vessel having a deck configured to support a tubular tool riser in a substantially horizontal position;

b) a winch at the deck which is configured to be connected to a wireline and wireline assembly;

c) means for inserting the wireline assembly and part the wireline through a first end of the tool riser into said riser such that the wireline passes along a riser sheave connected to the first end of the tool riser;

d) a crane that is configured to be connected to the first end of the tool riser and to lift the the tool riser in a substantially vertical position above the deck, whilst unreeling the wireline from the winch such that the wireline assembly remains located within the tool riser;

e) means for inducing the crane to move a second end of the tool riser above a guide sleeve which is connected to a side wall of the vessel adjacent to the deck;

f) a crane control mechanism for inducing the crane to lower the tool riser through the guide sleeve such that the second end of the tool riser is located subsea and the first end of the tool riser and the riser sheave are located above the deck; and

g) a crane heave compensation mechanism for controlling the motion of the tool riser and riser sheave relative to the seafloor while unreeling the wireline from the winch such that the wireline assembly is lowered from the tool riser through the water into the well.

8. The system of claim 7, wherein the first end of the tool riser is connected by a hoisting cable to a hook which is connected to a fall line of the crane.

9. The system of claim 8, wherein the hook is connected to a single fall line of the crane and the heave compensation mechanism is configured to maintain the the hook substantially stationary relative to the seafloor, thereby providing heave compensation to the wireline assembly.

10. The system of claim 8, wherein wireline passes through a deck sheave which is

connected to the deck adjacent to the sleeve and the hook is connected to a hoisting sheave which is connected by a double fall crane line to the crane and the heave compensation mechanism is configured to substantially halve reduce heave motion of the hook relative to heave motion of the vessel and inducing the deck sheave and riser sheave to provide heave compensation to the wireline assembly.

Description:
METHOD AND SYSTEM FOR WIRELINE INTERVENTION IN A SUBSEA WELL

FROM A FLOATING VESSEL

CROSS-REFERENCE TO RELATED APPLICATIONS

This application claims the benefit of U.S. Provisional Application No. 61/581,193, filed

December 29, 2011, and claims priority to European Patent Application No. 11196263.5, filed December 30, 2011, both of which are incorporated herein by reference.

BACKGROUND OF THE INVENTION

The invention relates to a method and system for wireline intervention in a subsea well from a floating vessel.

U.S. Patent No. 6,216,789 describes a method and system for wireline intervention in a subsea well from a floating vessel.

This prior art reference discloses a computer controlled heave compensation wireline logging winch system that compensates for the effects of wave motion on wireline tools suspended from floating vessels. Vessel vertical movement is measured and is physically compensated for by a change in speed of the wireline cable so that the logging data is obtained at a controlled speed. Any error in this physical compensation is detected by a depth measurement system and is used to adjust the true depth at which the logging tool measurements are being recorded.

There is a need to solve two problems associated with the method and system known from U.S. Patent No. 6,216,789:

(1) Overcome the challenges for upending and overboarding a long, fragile and flexible wireline toolstring from the deck of a floating vessel; and

(2) Accurately heave compensate the toolstring subsea in order to safely stab in the wireline tools into the subsea equipment and control at depth.

Traditionally, subsea well interventions are conducted from heavy-weight, mobile offshore drilling units (MODUs) with riser packages.

Unfortunately, these intervention operations demand substantial operating day rates.

Drilling units offers conventional means to assemble tool string in vertical position and stab in tools through riser packages, therefore heave compensation is usually not an issue. Apart from traditional rig interventions, rigless intervention have been carried out on light intervention vessels that also offers convention ways of assembly and deployment of toolstrings. On those types of vessel, heave compensation is sometimes incorporated to the derrick system itself. Thus there is a need for an improved wireline intervention method that can be performed from any floating vessel and which does not require use of a large drilling vessel and which overcomes the challenges for upending and overboarding a long, fragile and flexible wireline toolstring from the deck of a floating vessel.

SUMMARY OF THE INVENTION

In accordance with the invention there is provided a method for wireline intervention in an subsea well from a floating vessel, the method comprising:

a) arranging a tubular tool riser in a substantially horizontal position at a deck of the vessel; b) connecting a wireline assembly to a wireline that is connected to a winch arranged at the deck;

c) inserting the wireline assembly and pass the wireline through a first end of the tool riser into said riser such that the wireline passes along a riser sheave connected to the first end of the tool riser;

d) connecting the first end of the tool riser to a crane that lifts the tool riser in a substantially vertical position above the deck, whilst unreeling the wireline from the winch such that the wireline assembly remains located within the tool riser;

e) inducing the crane to move a second end of the tool riser above a guide sleeve which arranged and/or cantilevered off the side of the vessel;

f) inducing the crane to lower the tool riser through the guide sleeve such that the second end of the tool riser is located subsea and the first end of the tool riser and the riser sheave are located above the deck; and

g) inducing a crane heave compensation mechanism to control the motion of the tool riser and riser sheave relative to the seafloor while unreeling the wireline from the winch such that the wireline assembly is lowered from the tool riser through the water into the well.

The first end of the tool riser may be connected by a hoisting cable to a hook which is connected to a single fall line of the crane and the crane heave compensation mechanism is configured to maintain the hook substantially stationary relative to the seafloor, thereby providing heave compensation to the wireline assembly. Alternatively, the wireline passes through a deck sheave which is connected to the deck adjacent to the sleeve and the hook is connected to a hoisting sheave which is connected by a double fall crane line to the crane and the heave compensation mechanism is configured to substantially halve reduce heave motion of the hook relative to heave motion of the vessel and inducing the deck sheave and riser sheave to provide heave compensation to the wireline assembly.

In accordance with the invention there is further provided a system for wireline intervention into an subsea well from a floating vessel, the system comprising:

a) a floating vessel having a deck configured to support a tubular tool riser in a substantially horizontal position;

b) a winch at the deck which is configured to be connected to a wireline and wireline assembly;

c) means for inserting the wireline assembly and part the wireline through a first end of the tool riser into said riser such that the wireline passes along a riser sheave connected to the first end of the tool riser;

d) a crane that is configured to be connected to the first end of the tool riser and to lift the the tool riser in a substantially vertical position above the deck, whilst unreeling the wireline from the winch such that the wireline assembly remains located within the tool riser;

e) means for inducing the crane to move a second end of the tool riser above a guide sleeve which is connected to a side wall of the vessel adjacent to the deck;

f) a crane control mechanism for inducing the crane to lower the tool riser through the guide sleeve such that the second end of the tool riser is located subsea and the first end of the tool riser and the riser sheave are located above the deck; and

g) a crane heave compensation mechanism for controlling the motion of the tool riser and riser sheave relative to the seafloor while unreeling the wireline from the winch such that the wireline assembly is lowered from the tool riser through the water into the well.

These and other features, embodiments and advantages of the method and/or system according to the invention are described in the accompanying claims, abstract and the following detailed description of non-limiting embodiments depicted in the accompanying drawings, in which description reference numerals are used which refer to corresponding reference numerals that are depicted in the drawings.

Similar reference numerals in different figures denote the same or similar objects. BRIEF DESCRIPTION OF THE DRAWINGS

Figure 1 is a schematic side view of a first embodiment of a system according to the invention; and

Figure 2 is a schematic side view of a second embodiment of a system according to the invention.

DETAILED DESCRIPTION OF THE DEPICTED EMBODIMENTS

The system according to invention shown in figures 1 and 2 includes the following two inventive features I and Π:

I) The tool riser 1, which is a long joint of pipe with a quick connection flange welded to the first end of the riser 1A and a bevelled opposite end (second end of the riser IB). The tool riser 1 provides a means for the wireline toolstring 7A to be assembled in horizontal position into the tool riser 1 with the support of a work table, safely upended from horizontal to vertical position and finally deployed subsea. As soon as the tools are assembled and secured to the toolstring 7A they are inserted into the tool riser 1 through a quick connection flange at a first end 1A of the tool riser 1. Then the tool riser 1 is upended using a crane hook 2 and dedicated slings 3 connected to the first end 1A of the tool riser 1. This upending method does not offer any risk or damage to the tool strings 7A to be deployed.

II) The tool riser 1 is suspended by an active heave compensated crane hook 2 of a crane (not shown) mounted on the deck 4A of a floating vessel 4. When the heave compensation system on the crane is activated, the tool riser 1 is raised and lowered relative to the deck 4A of the floating vessel 4 keeping the tool string stationary relative to the seafloor, effectively isolating vessel motions from the tool string. As the wireline 7, which may comprises power and control cables or be a slickline without power and control cables, passes through the riser sheave 8 on the tool riser 1, compensation is transferred to the wireline 7.

The tool riser 1 moves up and down through a guide sleeve 5 attached to a work platform 6 cantilevered off the side 4B of the vessel 4. The sleeve 5 allows vertical motion of the tool riser 1, but prevents motion of the tool riser 1 in the horizontal plane. The arrangement of the tool riser 1 through the sleeve 5 prevents the tool riser 1 and crane hook 2 from swinging uncontrollably due to oscillating motions of the vessel 4 due to waves, wind and/or current. The tool riser 1 extends through the splash zone 9 into the water 11, which may be a sea, ocean or lake to protect the fragile toolstring 7A from damage due to wave action at the water surface.

There are two possible sheave arrangements that can be utilized depending on available deck space on the vessel 4 of opportunity.

Figure 1 shows the simple sheave arrangement, which arrangement requires more deck area than the more complex sheave arrangement shown in Figure 2.

Wireline operations on traditional drilling rigs compensate the toolstring 7A in a similar manner. In Figure 1, the crane hook 2 is suspended from a single fall crane line and is attached to the tool riser 1 by the slings 3 and operated in conventional heave compensation mode. The distance from the wireline winch 7B to the riser sheave 8 connected to the first end 1A of the tool riser 1 must be sufficient that when the tool riser 1 moves up and down with the crane hook 2 the change in distance between the wireline winch 7A and the tool riser 1 is negligible.

Figure 2 shows an alternate sheave arrangement which has been successfully used for an offshore well intervention. The crane hook 2 is connected to a double fall block 20, but the heave compensation system of the crane is operated in single fall mode. Therefore, the crane block 20 and hook 2 are only moving up and down half as much as they would normally move when the heave compensation system is activated. The movement on the crane block 20 and hook 2 is then multiplied by a factor of two with the sheave arrangement of a fixed sheave 21 on the work platform 6 and the riser sheave 8 on the tool riser 1, and the toolstring 7 A is properly heave compensated at the seafloor. This arrangement can be used when there is a limited horizontal distance between the wireline winch 7B and the tool riser 1.

It allows wireline operations to be performed from any vessel 4 of opportunity equipped with an active heave compensated crane hook 2 using a conventional wireline winch.