To contrive work cost reduction and construction period reduction without producing excessive temporary member related cost by enhancing safety without bringing secondary additional load on a structure during the erection work of new provision and repair.
In the erection method of a structure tensed to be mounted on the top part of a tower 2 and supporting a structure element member on a cable 3 connecting both-end anchor member 13 on the anchorage connection fitting 12 of an anchorage 5, the plural same number of cable fixing means 11, 12, 13 provided on each cable fixing part including the top part of the tower 2 and the anchorage 5 of both the ends are provided in same structure, a plurality of the cable fixing means are juxtaposed on the same cable fixing part in arrangement mutually approaching in the vertical direction and the horizontal direction so that a deviation amount is zero or the minimum.