Login| Sign Up| Help| Contact|

Patent Searching and Data


Title:
DEVICE FOR POSITIONING AND LIFTING A MARINE STRUCTURE, PARTICULARLY A PLATFORM DECK
Document Type and Number:
WIPO Patent Application WO/2000/075010
Kind Code:
A1
Abstract:
A device for positioning and lifting a marine structure, particularly a platform deck, with the use of a U-shaped lifting vessel (1). The device has at least two adjustable lifting frames (12, 12), each able to incline towards the middle of the docking area. Each of the lifting frames (12) consists of an upper horizontal lifting beam (13), preferably situated on a level above the top of the lifting vessel (1). The near-vertical part of the lifting frame (16) is connected to the lifting beam (13) in the upper end and in the lower end hinged (21) to the lifting vessel (1). The near-horizontal part of the lifting frame (18) is in one end connected to the lifting beam (13) and in the other end adjustably connected to the lifting vessel (1).

Inventors:
SCHIA JOHN (NO)
OLSEN TOR OLE (NO)
HOEYLAND KOLBJOERN (NO)
HAEREID KAARE O (NO)
HANSEN JOERN BASTHOLM (NO)
LANDBOE TROND (NO)
Application Number:
PCT/NO2000/000198
Publication Date:
December 14, 2000
Filing Date:
June 07, 2000
Export Citation:
Click for automatic bibliography generation   Help
Assignee:
MPU ENTPR AS (NO)
SCHIA JOHN (NO)
OLSEN TOR OLE (NO)
HOEYLAND KOLBJOERN (NO)
HAEREID KAARE O (NO)
HANSEN JOERN BASTHOLM (NO)
LANDBOE TROND (NO)
International Classes:
B63B9/06; E02B17/00; (IPC1-7): B63B35/44; E02B17/02
Foreign References:
US5829919A1998-11-03
US4714382A1987-12-22
US4744697A1988-05-17
Attorney, Agent or Firm:
BRYN & AARFLOT AS (P.O. Box 449 Sentrum Oslo, NO)
Download PDF:
Claims:
PATENT CLAIMS
1. A device for positioning and lifting a marine structure, particularly a platform deck, with the use of a Ushaped lifting vessel (1), c h a r a c t e r i s e d b y having at least two adjustable lifting frames (12,12), each able to incline towards the middle of the docking area. Each of the lifting frames (12) consists of an upper horizontal lifting beam (13), preferably situated on a level above the top of the lifting vessel (1). The nearvertical part of the lifting frame (16) is connected to the lifting beam (13) in the upper end and in the lower end hinged (21) to the lifting vessel (1). The nearhorizontal part of the lifting frame (18) is in one end connected to the lifting beam (13) and in the other end adjustably connected to the lifting vessel (1).
2. A device according to claim 1, c h a r a c t e r i s e d b y a shock absorbing cover (14) on the horizon tal lifting beam (13).
3. A device according to claim 2, c h a r a c t e r i s e d b y the shock absorbing cover (14) is made of rubber.
4. A device according to claim 1, c h a r a c t e r i s e d b y the lifting beam (13) is equipped with hy draulic cylinders (30) in predefined lifting point positions.
5. A device according to claim 1, c h a r a c t e r i s e d b y the lifting beam (13) is equipped with sand filled cylinders (35) in predefined lifting point positions since the sandfilled cylinders (35) are corresponding with the belonging coni cal tubular stubs (37) attached on the platform deck.
6. A device according to all of the above claims, c h a r a c t e r i s e d b y the lifting frame (16) is a truss structure.
7. A device according to all of the above claims, c h a r a c t e r i s e d b y the nearhorizontal structure (18) is a truss structure.
8. A device according to all of the above claims, c h a r a c t e r i s e d b y the nearhorizontal structures (18) having adjustable connection points to the lifting vessel (1) consisting of a hydraulically operated bolt (9) going into a corresponding hole (8) in a guiding rail (7) attached to the lifting vessel (1).
9. A device according to all of the above claims, c h a r a c t e r i s e d b y the lifting frames (16) in an area above the jointed bearing (21) are equipped with adjustable hydraulic arms (20) connected to the lifting vessel (1).
Description:
Device for positioning and lifting a marine structure, particularly a platform deck.

The present invention is related to a device for positioning and lifting a ma- rine structure, particularly a platform deck, with the help of a lifting vessel.

In connection with offshore activities such as gas and oil exploitation it is usual to install platforms on the field. These platforms often consist of large and heavy platform substructures fixed to the seabed. Such a platform sub- structure is normally a so-called"jacket", which is a steel truss structure. On top of for example a jacket it is usual to place a platform deck, which is used in connection with drilling and production. The deck also often includes liv- ing quarters.

To transport and install the jacket and the platform deck described above, for example barges have been used to transport the jacket and platform deck out to the field, and large crane vessels have been used to install the plat- form on the field.

Heavy lift vessels using ballast to vary their draft have also been used to transport and install platforms offshore.

There are today a great number of offshore platforms installed to exploit oil and gas. When the oil and/or gas reservoirs are fully exploited the life span of the platform is usually over and it would in most cases be appropriate to remove the platform.

Some platforms are already removed, and removal of platforms will con- tinue at an increasing pace the coming years.

The traditional way of removing platforms is to use large ocean going lifting cranes. The platform needs to be very thoroughly prepared prior to removal, and it must be cut into smaller parts since even the largest lifting crane ves- sels have limited lifting capacity. The same goes for the platform substruc- ture (the jacket).

These operations are time consuming and costly, not only because the lifting cranes are large, expensive and need a large crew, but also because cutting a

platform to smaller pieces in open sea is a very complicated task. It is also a risky operation.

The new technology, as described in this application, can be described as "single lift technology", and will reduce the costs considerably. It will also make the operations less risky than present alternatives. Within the category "single lift technology"there are three other concepts that the applicant is aware of at the moment: "Offshore Shuttle"is a vessel planned built as a frame work structure. The vessel has a significant length and the lifting of for example a platform deck is based on crossbeams spanning across the structure.

"Master Marine"is developing a U-shaped semi submersible with deck- structure connecting the top of columns. Lifting is based on load transfer to the deck-structure.

"Versatruss"is a concept involving two separate barges each supporting its own lifting frame. By pulling the barges together after positioning the lifting frames beneath the lifting points on the platform deck, the lifting of the deck can be performed. This method has already been used to remove small plat- form decks in calm waters.

One object of the present invention is to accomplish a removal operation of a platform in a fast and cost effective manner without cutting either the deck or the jacket into smaller parts. The removal operation shall be performed in a safe way where the safety of the operators is accomplished in the best pos- sible way.

Another object of the present invention is that the lifting and handling equipment is as flexible as possible and that it can be easily adjusted to fit different sized platform decks. Further the equipment shall be able to lift and handle jackets of different sizes. In accordance with the invention the device is intended to be used together with a vessel, a so-called Multi Purpose Unit, MPU, which also can transport e. g. the platform deck to shore, and then transfer the deck to a barge or a pier suitable to the vessel.

Another object of the device is that it also shall be able to be used for instal- lation of platforms, which basically is the reverse of removal. The device should furthermore be applicable for a range of purposes where a large lift- ing capacity is required.

The objects described above is achieved according to the invention by a de- vice for positioning and lifting a marine structure, particularly a platform deck, within the docking area of a lifting vessel recognised by having at least two adjustable lifting frames, each able to incline towards the middle of the docking area. Each of the lifting frames consists of an upper horizontal lifting beam, preferably situated on a level above the top of the lifting vessel. The near-vertical part of the lifting frame is connected to the lifting beam in the upper end and in the lower end hinged to the lifting ves- sel. The near-horizontal part of the lifting frame is in one end connected to the lifting beam and in the other end connected to the lifting vessel by a guide rail and an adjustable lock bolt.

Preferred embodiments of the device is described in the claims 2 to 9.

The present invention is described below by means of embodiments and with references to the figures, where: Fig. la shows a lifting vessel employed together with the device according to the present invention, Fig. lb shows the lifting vessel according to the present invention, Fig. 2 shows the lifting vessel positioned around a jacket with a platform deck, Fig. 3 shows a steel tubular rotation beam for lifting and rotating a jacket structure, Fig. 4 shows a device for lifting and rotating a jacket structure for installa- tion or removal, Fig. 5a-5c show the vessel in connection with lifting and rotating a jacket structure where a special"cradle"is used, Fig. 6 shows the device of the present invention in the form of lifting frames for lifting of preferably a platform deck, Fig. 7 shows hydraulic jacks for operating the lifting frame, situated between the lifting vessel and the inclined legs of the lifting frame and the figure also shows the steel tubular beam for lifting and rotation/removal of a jacket structure,

The objects described above is achieved according to the invention by a de- vice for positioning and lifting a marine structure, particularly a platform deck, within the docking area of a lifting vessel recognised by having at least two adjustable lifting frames, each able to incline towards the middle of the docking area. Each of the lifting frames consists of an upper horizontal lifting beam, preferably situated on a level above the top of the lifting vessel. The near-vertical part of the lifting frame is connected to the lifting beam in the upper end and in the lower end hinged to the lifting ves- sel. The near-horizontal part of the lifting frame is in one end connected to the lifting beam and in the other end connected to the lifting vessel by a guide rail and an adjustable lock bolt.

Preferred embodiments of the device is described in the claims 2 to 9.

The present invention is described below by means of embodiments and with references to the figures, where: Fig. la shows a lifting vessel employed together with the device according to the present invention, Fig. lb shows the lifting vessel according to the present invention, Fig. 2 shows the lifting vessel positioned around a jacket with a platform deck, Fig. 3 shows a steel tubular rotation beam for lifting and rotating a jacket structure, Fig. 4 shows a device for lifting and rotating a jacket structure for installa- tion or removal, Fig. 5a-5c show the vessel in connection with lifting and rotating a jacket structure where a special"cradle"is used, Fig. 6 shows the device of the present invention in the form of lifting frames for lifting of preferably a platform deck, Fig. 7 shows hydraulic jacks for operating the lifting frame, situated between the lifting vessel and the inclined legs of the lifting frame and the figure also shows the steel tubular beam for lifting and rotation/removal of a jacket structure,

Fig. 8 shows a hydraulic lock bolt system for locking of the lifting frame in a certain position to a guide rail connected to the lifting vessel, Fig. 9 shows one first alternative for a connection between the lifting frame and the jacket structure for removal of a platform deck, Fig. 10a and 10b show a second alternative for a connection between the lifting frame and the jacket structure for removal of a platform deck, Fig. 1 la and 1 lb show a third alternative for a connection between the lift- ing frame and the jacket structure for removal of a platform deck, Fig. 12,13,14 and 15 show step by step the operation sequence for removal of a platform deck with the help of the lifting vessel, and Fig. 16,17,18,19 and 20 show step by step the operation sequence for re- moval of a jacket structure with the help of the lifting vessel.

The device according to the present invention will now be described with reference to the figures, especially fig. la and 2.

The device according to the present invention will now be described in con- nection with a lifting vessel protected through the Norwegian patent applica- tion no. 99 2759 held by the applicant of the present invention. The device according to the present invention is therefore described in connection with this lifting vessel, however it shall be noted that the device can be applied with other vessels and other equipment.

The lifting vessel 1 (MPU) is developed as a floating concrete hull with a U- shaped pontoon foundation 2 containing two longitudinal pontoons 2a, 2b and a transverse pontoon 2c, and with columns 5 through the water surface for hydrostatic stability and optimal behaviour in the sea. The columns 5 are not connected structurally at the top, which is made possible by a rigid and robust hull structure. A brim 3 along the lower edge of the pontoon founda- tion improves further the behaviour of the vessel in the sea. The vessel 1 is specially developed for operations offshore. The U-shape of the pontoon foundation 2a, 2b, 2c enables the vessel to position itself around a platform being installed or a platform being removed, be it the platform deck or a platform substructure. The lifting operation is performed according to Ar- chimedes'principle by ballasting/deballasting the vessel 1. The lifting is mainly performed vertically, but the vessel 1 can be inclined in all directions to enable special lifting operations.

Fig. 8 shows a hydraulic lock bolt system for locking of the lifting frame in a certain position to a guide rail connected to the lifting vessel, Fig. 9 shows one first alternative for a connection between the lifting frame and the jacket structure for removal of a platform deck, Fig. 10a and 10b show a second alternative for a connection between the lifting frame and the jacket structure for removal of a platform deck, Fig. 1 la and 1 lb show a third alternative for a connection between the lift- ing frame and the jacket structure for removal of a platform deck, Fig. 12,13,14 and 15 show step by step the operation sequence for removal of a platform deck with the help of the lifting vessel, and Fig. 16,17,18,19 and 20 show step by step the operation sequence for re- moval of a jacket structure with the help of the lifting vessel.

The device according to the present invention will now be described with reference to the figures, especially fig. la and 2.

The device according to the present invention will now be described in con- nection with a lifting vessel protected through the Norwegian patent applica- tion no. 99 2759 held by the applicant of the present invention. The device according to the present invention is therefore described in connection with this lifting vessel, however it shall be noted that the device can be applied with other vessels and other equipment.

The lifting vessel 1 (MPU) is developed as a floating concrete hull with a U- shaped pontoon foundation 2 containing two longitudinal pontoons 2a, 2b and a transverse pontoon 2c, and with columns 5 through the water surface for hydrostatic stability and optimal behaviour in the sea. The columns 5 are not connected structurally at the top, which is made possible by a rigid and robust hull structure. A brim 3 along the lower edge of the pontoon founda- tion improves further the behaviour of the vessel in the sea. The vessel 1 is specially developed for operations offshore. The U-shape of the pontoon foundation 2a, 2b, 2c enables the vessel to position itself around a platform being installed or a platform being removed, be it the platform deck or a platform substructure. The lifting operation is performed according to Ar- chimedes'principle by ballasting/deballasting the vessel 1. The lifting is mainly performed vertically, but the vessel 1 can be inclined in all directions to enable special lifting operations.

Positioning of the vessel 1 is considered done by tugs, but thrusters can be installed to make the vessel 1 self-propulsive. The vessel 1 is designed to operate in all oceans in all parts of the world. The vessel 1 is also designed to be transported on a heavy lift ship to ease transportation over large dis- tances.

The vessel 1 is equipped with devices specially fitted for the operations the vessel 1 is intended for. Installation and removal of platforms (platform decks and platform substructures) for the oil and gas industry are examples of operations the vessel 1 is intended for.

Installation and removal of platform substructures are mentioned above as fields of operation for the vessel 1. The vessel 1 will now be described in relation to these operations, especially in connection with the handling of jackets. Steel jackets are widely used all over the world in the oil and gas industry as substructure for offshore oil and gas production units. There are also many other situations where a jacket structure is suitable as a support structure. There will be a market for both installation and removal of jackets in the future. Below is described operations concerning removal of a jacket.

For installation the operations will be performed in the reverse order.

Lifting brackets 25 are attached to the jacket legs on one side of the jacket at a certain, pre-established height. A circular tubular rotation beam 22 is fixed to the top of the transverse pontoon 2c of the lifting vessel 1. The lifting vessel 1 is positioned around the jacket with the help of tugs and active use of a device according to the present invention, a lifting frame 12. This de- vice will be described more thoroughly later in connection with lifting de- vices for positioning and lifting of a platform deck. The vessel 1 is hauled to a position where the transverse pontoon 2c of the vessel 1 is positioned close to the side of the jacket where the lifting brackets 25 are attached. The lifting vessel is ballasted to the desired draft and inclination of heel so that the tubular rotation beam 22 connects with the lifting brackets 25, see fig. 4, concurrent with the lower edge of the transverse pontoon 2c bear against the jacket legs with fenders between them. The lifting brackets 25 are locked to the tubular rotation beam 22 and by deballasting the lifting vessel 1 the jacket is lifted. When the jacket is lifted clear of the seabed or foundation the lower part is lifted to the surface using wires and winches (or buoyancy modules), thereby rotating the jacket about the tubular rotation beam 22, be- fore transportation to a new destination.

Positioning of the vessel 1 is considered done by tugs, but thrusters can be installed to make the vessel 1 self-propulsive. The vessel 1 is designed to operate in all oceans in all parts of the world. The vessel 1 is also designed to be transported on a heavy lift ship to ease transportation over large dis- tances.

The vessel 1 is equipped with devices specially fitted for the operations the vessel 1 is intended for. Installation and removal of platforms (platform decks and platform substructures) for the oil and gas industry are examples of operations the vessel 1 is intended for.

Installation and removal of platform substructures are mentioned above as fields of operation for the vessel 1. The vessel 1 will now be described in relation to these operations, especially in connection with the handling of jackets. Steel jackets are widely used all over the world in the oil and gas industry as substructure for offshore oil and gas production units. There are also many other situations where a jacket structure is suitable as a support structure. There will be a market for both installation and removal of jackets in the future. Below is described operations concerning removal of a jacket.

For installation the operations will be performed in the reverse order.

Lifting brackets 25 are attached to the jacket legs on one side of the jacket at a certain, pre-established height. A circular tubular rotation beam 22 is fixed to the top of the transverse pontoon 2c of the lifting vessel 1. The lifting vessel 1 is positioned around the jacket with the help of tugs and active use of a device according to the present invention, a lifting frame 12. This de- vice will be described more thoroughly later in connection with lifting de- vices for positioning and lifting of a platform deck. The vessel 1 is hauled to a position where the transverse pontoon 2c of the vessel 1 is positioned close to the side of the jacket where the lifting brackets 25 are attached. The lifting vessel is ballasted to the desired draft and inclination of heel so that the tubular rotation beam 22 connects with the lifting brackets 25, see fig. 4, concurrent with the lower edge of the transverse pontoon 2c bear against the jacket legs with fenders between them. The lifting brackets 25 are locked to the tubular rotation beam 22 and by deballasting the lifting vessel 1 the jacket is lifted. When the jacket is lifted clear of the seabed or foundation the lower part is lifted to the surface using wires and winches (or buoyancy modules), thereby rotating the jacket about the tubular rotation beam 22, be- fore transportation to a new destination.

The lifting brackets 25 are made of steel of robust design and will absorb all forces introduced by the lifting and rotating operations. The lifting brackets 25 are designed to lock onto the tubular rotation beam. The lifting brackets 25 easily rotate on the tubular rotation beam 22.

Pre-engineering is required with regards to the strength of the jacket struc- ture before a lift can take place. The jacket legs must be reinforced if they cannot endure the loads introduced. The lifting brackets 25 can, if necessary, be shaped with two long tubular clamps with a plate between them, so that they can be mounted to the main leg and a diagonal bracing of the jacket.

The brackets 25 will then absorb the forces from the tubular rotation beam 22 and distribute them to the tubular clamps, which in turn distribute the forces onward in axial direction of the legs and the braces of the jacket, and so avoiding the largest shear forces. This device must be dimensioned for each individual case.

For some jackets it may be difficult to dimension the support for the brack- ets 25. If this is a problem a"lifting cradle"according to the invention can be used, see fig. 5. The lifting cradle is attached to the tubular rotation beam 22 and uses this as a rotation point as described above. The cradle 29 is a framework consisting of two triangular frames pointing outwards with a pointed end upwards, attached to the tubular rotation beam 22 on the pon- toon. The triangular frames are connected with a tubular beam at the bottom of the perpendicular. The cradle 29 consists of tubes 2-3 meters in diameter that are filled with water when the cradle 29 is in its lowest position and will be emptied when the lift starts. The large dimensions secure structural strength and enough buoyancy to contribute to the lift.

The lifting vessel 1 is positioned as described above and the cradle 29 will embrace the jacket. Specially adjusted saddles are attached to the lower cir- cular beam on the cradle 29, resting against the jacket legs. To avoid the jacket from sliding off the cradle 29 during the lift the jacket is connected to the tubular rotation beam 22 through brackets attached to the jacket legs. On the back of the lifting vessel 1 winches are mounted on each side of the "docking area"i. e. the inner area of the U-shaped pontoon foundation sur- rounded by the two longitudinal pontoons 2a, 2b and the transversal pontoon 2c. Winches onboard tugs can also be used. Through pulleys wires with a hook in one end is hooked to the lower corners of the cradle 29. The cradle 29 is now lifted upwards rotating about the tubular rotation beam 22 and the jacket is lifted out of the water for safe transportation to shore. An alterna- tive method is to ballast/deballast the vessel 1 combined with the use of buoyancy modules attached to the jacket.

The lifting brackets 25 are made of steel of robust design and will absorb all forces introduced by the lifting and rotating operations. The lifting brackets 25 are designed to lock onto the tubular rotation beam. The lifting brackets 25 easily rotate on the tubular rotation beam 22.

Pre-engineering is required with regards to the strength of the jacket struc- ture before a lift can take place. The jacket legs must be reinforced if they cannot endure the loads introduced. The lifting brackets 25 can, if necessary, be shaped with two long tubular clamps with a plate between them, so that they can be mounted to the main leg and a diagonal bracing of the jacket.

The brackets 25 will then absorb the forces from the tubular rotation beam 22 and distribute them to the tubular clamps, which in turn distribute the forces onward in axial direction of the legs and the braces of the jacket, and so avoiding the largest shear forces. This device must be dimensioned for each individual case.

For some jackets it may be difficult to dimension the support for the brack- ets 25. If this is a problem a"lifting cradle"according to the invention can be used, see fig. 5. The lifting cradle is attached to the tubular rotation beam 22 and uses this as a rotation point as described above. The cradle 29 is a framework consisting of two triangular frames pointing outwards with a pointed end upwards, attached to the tubular rotation beam 22 on the pon- toon. The triangular frames are connected with a tubular beam at the bottom of the perpendicular. The cradle 29 consists of tubes 2-3 meters in diameter that are filled with water when the cradle 29 is in its lowest position and will be emptied when the lift starts. The large dimensions secure structural strength and enough buoyancy to contribute to the lift.

The lifting vessel 1 is positioned as described above and the cradle 29 will embrace the jacket. Specially adjusted saddles are attached to the lower cir- cular beam on the cradle 29, resting against the jacket legs. To avoid the jacket from sliding off the cradle 29 during the lift the jacket is connected to the tubular rotation beam 22 through brackets attached to the jacket legs. On the back of the lifting vessel 1 winches are mounted on each side of the "docking area"i. e. the inner area of the U-shaped pontoon foundation sur- rounded by the two longitudinal pontoons 2a, 2b and the transversal pontoon 2c. Winches onboard tugs can also be used. Through pulleys wires with a hook in one end is hooked to the lower corners of the cradle 29. The cradle 29 is now lifted upwards rotating about the tubular rotation beam 22 and the jacket is lifted out of the water for safe transportation to shore. An alterna- tive method is to ballast/deballast the vessel 1 combined with the use of buoyancy modules attached to the jacket.

The present device for positioning and lifting of a platform deck will now be described with reference to the drawings. Platform decks exist in different sizes and to be able to handle them all, the lifting device must be large, strong and flexible/adjustable, with strict requirements to the shape for posi- tioning around the substructure carrying the deck.

Lifting frame 12 according to a design of the present invention is fitted with a horizontal robust lifting beam 13 at the top and is pin-connected 21 to the top of the longitudinal pontoons 2a, 2b on each side of the docking area, see fig. 1. The lifting frame 12 consists of a near-horizontal structure 18, pref- erably a truss structure, going from the horizontal lifting beam 13 to the up- per anchorage point 10 on the lifting vessel 1. Furthermore the lifting frame 12 consists of a vertical support structure 16, preferably a truss-work, con- nected in its upper end to the lifting beam 13 and connected in its lower end to the lifting vessel through an anchorage point 11, preferably a pin connec- tion 21. The lifting frames 12,12 in the upright position stands taller than the top of the lifting vessel 1, such that the lifting beams 13,13 are always above the hull of the lifting vessel 1. The lifting frames 12,12 can, with the use of the hydraulic cylinders 20,20 connected to the lifting vessel 1 and the lifting frames 12,12, see fig. la and 7, be inclined towards the middle of the docking area to position the lifting beams 13,13 under the lifting points on the platform deck. The two lifting frames 12,12 can be run independently.

The lifting frames 12,12 are locked in the right position before the lift starts, with hydraulic bolts 9 through holes 8 in guide rails 7 connected to each of the four columns 5 on the hull of the lifting vessel 1, see fig. la and 8. This ensures fixation in all directions included sea fastening during trans- port. Plane outer walls 6 tangentially fixed to the columns 5 are supporting the guide rails 7. The plane walls 6 are furthermore perpendicular to the di- rection of the connection line between two columns 5,5.

The connection between the lifting beam 13 and the deck can be carried out in different ways. Below is described three ways that ensures adequate flex- ibility to absorb shocks during a lift off: i) The lifting beam 13 can be equipped with a shock absorbing cover 14 while also placing shock absorbing cushions underneath the deck. If it is not possible to lift directly underneath the deck the upper part of the jacket can be fitted with brackets 26 with shock cushions so that the lifting beam 13 can get a proper hold, see fig. 9. Prior to lift off the jacket will be cut right below the brackets 26.

The present device for positioning and lifting of a platform deck will now be described with reference to the drawings. Platform decks exist in different sizes and to be able to handle them all, the lifting device must be large, strong and flexible/adjustable, with strict requirements to the shape for posi- tioning around the substructure carrying the deck.

Lifting frame 12 according to a design of the present invention is fitted with a horizontal robust lifting beam 13 at the top and is pin-connected 21 to the top of the longitudinal pontoons 2a, 2b on each side of the docking area, see fig. 1. The lifting frame 12 consists of a near-horizontal structure 18, pref- erably a truss structure, going from the horizontal lifting beam 13 to the up- per anchorage point 10 on the lifting vessel 1. Furthermore the lifting frame 12 consists of a vertical support structure 16, preferably a truss-work, con- nected in its upper end to the lifting beam 13 and connected in its lower end to the lifting vessel through an anchorage point 11, preferably a pin connec- tion 21. The lifting frames 12,12 in the upright position stands taller than the top of the lifting vessel 1, such that the lifting beams 13,13 are always above the hull of the lifting vessel 1. The lifting frames 12,12 can, with the use of the hydraulic cylinders 20,20 connected to the lifting vessel 1 and the lifting frames 12,12, see fig. la and 7, be inclined towards the middle of the docking area to position the lifting beams 13,13 under the lifting points on the platform deck. The two lifting frames 12,12 can be run independently.

The lifting frames 12,12 are locked in the right position before the lift starts, with hydraulic bolts 9 through holes 8 in guide rails 7 connected to each of the four columns 5 on the hull of the lifting vessel 1, see fig. la and 8. This ensures fixation in all directions included sea fastening during trans- port. Plane outer walls 6 tangentially fixed to the columns 5 are supporting the guide rails 7. The plane walls 6 are furthermore perpendicular to the di- rection of the connection line between two columns 5,5.

The connection between the lifting beam 13 and the deck can be carried out in different ways. Below is described three ways that ensures adequate flex- ibility to absorb shocks during a lift off: i) The lifting beam 13 can be equipped with a shock absorbing cover 14 while also placing shock absorbing cushions underneath the deck. If it is not possible to lift directly underneath the deck the upper part of the jacket can be fitted with brackets 26 with shock cushions so that the lifting beam 13 can get a proper hold, see fig. 9. Prior to lift off the jacket will be cut right below the brackets 26.

ii) Hydraulic cylinders 30 are placed on top of the lifting beam 13 in well calculated positions to get direct contact with the lifting points on the deck structure (or brackets 26 on the upper part of the jacket). Shock absorbing cushions are placed between the deck structure and the hy- draulic cylinders 30 to obtain maximum damping, see fig. 10. iii)"Shock cells"consisting of cylinders 35 filled with sand or another shock absorbing material is placed on top of the lifting beams 13 in well calculated positions. Conical tube stubs 37 are placed in corre- sponding positions on the deck structure. The conical tube stubs 37 absorb shocks when they penetrate the sand-filled cylinders 35, see fig. 1 la. An alternative is that both the tube stubs 37 and the shock cells 35 are mounted on the deck structure, see fig. 1 lb.

The MPU 1 is positioned around a jacket structure with deck and is made ready for lift off and removal of the deck. The lifting frames 12,12 on each side of the docking area is actively used for positioning by inclining them against the jacket with the help of hydraulically controlled arms 20, see fig.

2. Additionally the positioning is done by tugs. The lifting frames 12,12 are pulled back into lifting position when the MPU 1 is in the right position, as described above. The MPU 1 is then deballasted slowly until the lifting beams 13 are touching the lifting points. Compensation for the vertical mo- tions of the MPU 1 is partly done by flexible shock cushions mounted on the lifting beams and lifting points, and partly by the use of a flushing system that ensures a quick load transfer. When the deck has a safe clearance to the jacket the MPU is pulled away from the jacket before ballasted down to transport draft.

The flushing system consists of flushing (ballast) tanks 4 above the water- line with large area quick release trapdoors that enable the water to flush out. Trapdoors on different levels enable multiphase flushing, i. e. flushing in several steps.

This example describes the operations for removal of a platform deck. The different operations are illustrated in a sequence of figures; fig. 12-15: i) Positioning around a jacket with a deck.

With the help of tugs the MPU 1 is positioned around the jacket. The lifting frames 12,12 are in upright position with good clearance to the jacket. The draft of the vessel 1 ensures good clearance to the deck, see fig. 12.

ii) Using the lifting frames 12,12 to fine adjust the position around the jacket.

When the MPU 1 is approaching the correct position the lifting fra- mes 12,12 are inclined against the jacket to dampen the horizontal motions of the MPU 1 and also to fine-adjust the position. This is done by active use of hydraulics, see fig. 13. iii) Deballasting the MPU 1, ready for lift-off.

The MPU 1 is deballasted while the lifting frames 12,12 glide along the jacket structure to dampen the horizontal motions. The deballast- ing proceeds until the lifting frames 12,12 are right under the lifting points on the deck. The lifting frames 12,12 are then locked into posi- tion and MPU 1 is ready for lifting off the platform deck, see fig. 14. iv) Lift-off of the deck When the MPU 1 is ready to lift off the deck, water in the flushing tanks 4 are let out quickly by opening the quick release trapdoors in the columns 5 thereby achieving a rapid lift. The deck is prepared in advance by cutting the connections between the deck and the jacket, see fig. 15. v) Ready for transportation to shore After lift-off the MPU 1 is pulled away from the remaining jacket.

The MPU 1 is deballasted down to transportation draft when it is clear from the jacket. If necessary additional sea fastening to the locking of the lifting frames 12,12 are added and the transportation to shore can start. It is also possible to transfer the deck to a barge for transporta- tion to shore so that the MPU 1 is immediately available for new op- erations (e. g. removal of the jacket).

This example describes the operations for removal of a jacket structure. The different operations are illustrated in a sequence of figures; fig. 16-20: vi) Positioning around a jacket (without a deck).

With help from tugs the MPU 1 is positioned around the jacket. The lifting frames 12,12 are in upright position with good clearance to the jacket, see fig. 16. vii) Using the lifting frames 12,12 to fine adjust the position around the jacket.

When the MPU 1 is approaching the correct position the lifting fra- mes 12,12 are inclined against the jacket to dampen the horizontal motions of the MPU 1 and also to fine-adjust the position. This is done by active use of hydraulics, see fig. 17. viii) The MPU is inclined and deballasted, ready for lift-off

ii) Using the lifting frames 12,12 to fine adjust the position around the jacket.

When the MPU 1 is approaching the correct position the lifting fra- mes 12,12 are inclined against the jacket to dampen the horizontal motions of the MPU 1 and also to fine-adjust the position. This is done by active use of hydraulics, see fig. 13. iii) Deballasting the MPU 1, ready for lift-off.

The MPU 1 is deballasted while the lifting frames 12,12 glide along the jacket structure to dampen the horizontal motions. The deballast- ing proceeds until the lifting frames 12,12 are right under the lifting points on the deck. The lifting frames 12,12 are then locked into posi- tion and MPU 1 is ready for lifting off the platform deck, see fig. 14. iv) Lift-off of the deck When the MPU 1 is ready to lift off the deck, water in the flushing tanks 4 are let out quickly by opening the quick release trapdoors in the columns 5 thereby achieving a rapid lift. The deck is prepared in advance by cutting the connections between the deck and the jacket, see fig. 15. v) Ready for transportation to shore After lift-off the MPU 1 is pulled away from the remaining jacket.

The MPU 1 is deballasted down to transportation draft when it is clear from the jacket. If necessary additional sea fastening to the locking of the lifting frames 12,12 are added and the transportation to shore can start. It is also possible to transfer the deck to a barge for transporta- tion to shore so that the MPU 1 is immediately available for new op- erations (e. g. removal of the jacket).

This example describes the operations for removal of a jacket structure. The different operations are illustrated in a sequence of figures; fig. 16-20: vi) Positioning around a jacket (without a deck).

With help from tugs the MPU 1 is positioned around the jacket. The lifting frames 12,12 are in upright position with good clearance to the jacket, see fig. 16. vii) Using the lifting frames 12,12 to fine adjust the position around the jacket.

When the MPU 1 is approaching the correct position the lifting fra- mes 12,12 are inclined against the jacket to dampen the horizontal motions of the MPU 1 and also to fine-adjust the position. This is done by active use of hydraulics, see fig. 17. viii) The MPU is inclined and deballasted, ready for lift-off

The MPU 1 is inclined and deballasted until the tubular rotation beam 22, situated on top of the transversal pontoon 2c, gets a hold of the brackets 25 pre-installed on the jacket, see fig. 18. ix) Lift-off When the MPU 1 is ready to lift off the jacket, water in the flushing tanks 4 are let out quickly by opening the quick release trapdoors in the columns 5 thereby achieving a rapid lift. The jacket is prepared in advance by cutting the jacket legs, piles, risers etc., see fig. 19. x) Tilting of the jacket, ready for transportation After lift-off, the jacket is rotated to a near-horizontal position with the use of winches and wires mounted on the aft of the MPU 1 or winches and wires onboard tugs, see fig. 20. An alternative method is to attach buoyancy modules to the jacket. After sea fastening the transportation to shore can start. An alternative is to transfer the jacket to a barge for transportation to shore so that the MPU 1 is immedi- ately available for new operations.